Benefits realisation example: baseline, target and progress
A worked example using the fictional Atlas Data Centre Modernisation programme. The organisation, people and figures are made up to show the method; they are not customer results.
Fictional example. Atlas is an illustrative programme used in the ProjectScope 360 demo.
How progress is calculated
Progress is the share of the gap between baseline and target achieved so far: (current − baseline) ÷ (target − baseline). It works whether the aim is to increase a measure, such as availability, or reduce one, such as recovery time.
| Benefit | Baseline | Target | Current | Progress | Owner |
|---|---|---|---|---|---|
Annual run-cost reduction Infrastructure run cost per year | 0 £k | 1600 £k | 520 £k | 33% | Finance Business Partner |
Power usage reduction kWh per month vs FY25 | 0 % | 40 % | 18 % | 45% | Sustainability Lead |
Service availability Tier-1 availability | 99.5 % | 99.95 % | 99.9 % | 89% | Head of Operations |
Mean time to recover MTTR for P1 incidents | 6 hrs | 2 hrs | 5 hrs | 25% | Head of Operations |
What to take from it
Each benefit has one measurable value, a named owner and a review date that falls after handover. Recovery time is furthest behind, so it would be the benefit to discuss at the next steering meeting.