Benefits realisation example: baseline, target and progress

A worked example using the fictional Atlas Data Centre Modernisation programme. The organisation, people and figures are made up to show the method; they are not customer results.

Fictional example. Atlas is an illustrative programme used in the ProjectScope 360 demo.

How progress is calculated

Progress is the share of the gap between baseline and target achieved so far: (current − baseline) ÷ (target − baseline). It works whether the aim is to increase a measure, such as availability, or reduce one, such as recovery time.

Fictional Atlas benefits with baseline, target and current values
BenefitBaselineTargetCurrentProgressOwner
Annual run-cost reduction
Infrastructure run cost per year
0 £k1600 £k520 £k
33%
Finance Business Partner
Power usage reduction
kWh per month vs FY25
0 %40 %18 %
45%
Sustainability Lead
Service availability
Tier-1 availability
99.5 %99.95 %99.9 %
89%
Head of Operations
Mean time to recover
MTTR for P1 incidents
6 hrs2 hrs5 hrs
25%
Head of Operations

What to take from it

Each benefit has one measurable value, a named owner and a review date that falls after handover. Recovery time is furthest behind, so it would be the benefit to discuss at the next steering meeting.