Benefits realisation: set a baseline and target before you start

Track benefits realisation with a baseline, target, owner and review date. See a fictional worked example and explore ProjectScope 360 Pro reporting.

One measure per benefit

A benefit such as 'improved resilience' cannot be tracked. Turn it into one measure with a unit, such as Tier-1 availability in per cent or mean time to recover in hours.

Capture the baseline before delivery begins. Without it, nobody can show what changed.

Measure progress against the gap

Progress is the share of the gap between baseline and target achieved so far. That works whether the measure should rise, like availability, or fall, like recovery time.

Name an owner who will still be responsible after the project closes, and set a review date after handover.

See a worked example

Our fictional benefits realisation example shows four benefits from the Atlas demo programme with baseline, target, current value and progress.