Atlas Data Centre Modernisation
Live alerts (3)
Fictional example · As of 2026-11-16
- Budget forecast above threshold
£510,000 (6.1%) over baseline · threshold 5%
- Firewall rule-base complexity delays wave 3
Risk · score 20 · owner Marcus Lee
- Inter-site latency above 8 ms during peak
Issue · score 16 · 6 days overdue · owner Marcus Lee
Scope & Planning
Budget tracking
Atlas Data Centre Modernisation
Budget baseline, actuals & forecast
- Baseline
- £8,400,000
- Actual spend
- £4,870,000
- Forecast at completion
- £8,910,000
- Remaining baseline
- £3,530,000
- Forecast spend remaining
- £4,040,000
- Actual vs total baseline
- -£3,530,000
Amber
Forecast variance: £510,000 (6.1%) — exceeds 5%; review the forecast.
Actual spend is cumulative, not variance against a phased plan. Forecast is the recorded estimate at completion.
CSV import is available to workspace members with edit rights on live projects.