AI insights
Project intelligence
Atlas Data Centre Modernisation
Live alerts (3)
Fictional example · As of 2026-11-16
- Budget forecast above threshold
£510,000 (6.1%) over baseline · threshold 5%
- Firewall rule-base complexity delays wave 3
Risk · score 20 · owner Marcus Lee
- Inter-site latency above 8 ms during peak
Issue · score 16 · 6 days overdue · owner Marcus Lee
Forward outlook · 16 Nov 2026
Recorded completion forecast
£8.9m
£4,040,000 remaining against actuals
Constant-spend scenario
£8.7m
Actual spend ÷ elapsed project time. Assumes even spend; not an approved forecast.
Next 30 days
1
1 milestones marked at risk or blocked
Upcoming milestones
Wave 3 cut-over
11 Dec 2026 · Priya Shah · At risk · Dependency: CAB-0457 approval
Priority risk exposure
Firewall rule-base complexity delays wave 3 · 20/25
Marcus Lee · Rationalise rules in two sprints; add second security engineer.
Legacy app licence not portable to cloud · 9/25
Priya Shah · Vendor negotiation; fallback to colocation.
AI insights configuration
AI analysis requires a signed-in workspace with stored records.